The LA County Metropolitan Transportation Authority (LA Metro) will oversee the removal of 14 trees on West Colorado Boulevard to further the plans of the North Hollywood to Pasadena Bus Rapid Transit (BRT) project. A meeting on this topic will be held by LA Metro Nov. 19 at Occidental in the Herrick Interfaith Center.
According to the official LA Metro website, the BRT is a lane construction project that will create dedicated bus and bike lanes across North Hollywood, Burbank, Glendale, Eagle Rock and Pasadena to provide faster, more reliable bus service.
According to Darren Gold, President of the Historic Highland Park Neighborhood Council, the trees being removed are close enough to the road to be in the way of lane construction.
“My understanding is that the 14 trees proposed for removal are in the center median and along the sidewalks within the 1500–2700 blocks of West Colorado Boulevard in Eagle Rock,” Gold said via email.
Gold said community members are concerned about the trees being removed because they are old and provide considerable canopy coverage.
“We’re very happy that Metro plans to plant 86 new trees, far more than are being removed,” Gold said via email. “Our concern is the loss of mature trees and the time it will take for the new ones to provide comparable shade.”

According to Gold, feelings about the BRT extend far beyond the trees and are heavily mixed among the community.
“It’s not a black-and-white issue,” Gold said via email. “Many of the improvements could be beneficial, but there are also concerns about traffic and access to the businesses along Colorado Boulevard, which many of us frequent.”
According to Eagle Rock resident Nadine Levyfield, who began the change.org petition to withhold permits from Metro until they share project details with the public, some community members are concerned about a perceived lack of transparency with the project and how it will affect the area.
“It’s not the tree removal/lane plans that are opposed — we support Metro and BRT,” Levyfield said via email. “We are not anti-transit. However, the lack of transparency from Metro and lack of opportunity for real community input is problematic.”
Levyfield said this lack of transparency raises concerns about the amount of forethought and planning that went into ensuring the BRT project is not detrimental for the Eagle Rock area.
“We just found out that Metro’s 2022 traffic study relied entirely on computer modeling, with no real-world traffic testing, and did not include projections for Hill Drive or Yosemite Drive— two streets likely to absorb diverted traffic from Colorado Boulevard,” Levyfield said via email.
According to Levyfield, the BRT will not interact with Colorado Boulevard in the same way as other areas it will run through.
“Colorado Boulevard is not like the other commercial corridors along the BRT route,” Levyfield said via email. “Eagle Rock has a 1.7-mile downtown district lined with independently owned businesses, one public parking lot with approximately 30 spaces and residential streets — not parallel commercial thoroughfares to absorb additional traffic.”
Levyfield said via email that she is worried the BRT project will put the lives of Eagle Rock residents at risk.
“My greatest concern is not daily traffic inconvenience,” Levyfield said via email. “It is the possibility of preventable injuries and fatalities. I worry about children walking to school, families crossing neighborhood streets and frustrated drivers speeding through residential areas to avoid gridlock.”
Levyfield said Metro will hold two meetings this week, one online and one in-person.
“Metro is hosting a virtual meeting Nov. 18 and an in person meeting at the Occidental Herrick Interfaith Center Nov. 19,” Levyfield said via email. “These are quarterly project updates for the entire NOHO to Pasadena BRT route, so residents from NOHO, Burbank, Glendale, Pasadena and Eagle Rock will be there to seek project details from Metro.”
According to Talha Aamir, a board member on the Eagle Rock Neighborhood Council (ERNC), the Eagle Rock neighborhood owes a lot of its positive qualities to the streetcar system it was built upon.
“From my perspective, the BRT is a spiritual successor to [the streetcar system], and I hope that the future of the neighborhood will reflect how it was built originally,” Aamir said.
According to Aamir, construction for the BRT project is set to begin around the same time that a transportation bill called SB79 goes into effect, which interacts with the BRT in a way that would call for the upzoning of many properties on Colorado Boulevard.
“[There are going to be] three stations that are coming into the neighborhood,” Aamir said. “[The BRT] is also going to be paired with SB79, which is the housing bill which upzones almost all properties within half a mile of a major transit station […] Come 2030, 2031, […] a majority of the neighborhood is going to be upzoned to six-to-eight-story buildings.”
According to Levyfield, the neighborhood of Eagle Rock deserves a design that reflects its infrastructure, and the BRT project could put that in jeopardy.
“The project proposes removing 198 parking spaces and [14] mature trees,” Levyfield said via email. “These changes, combined with approximately two years of construction, could have lasting consequences for small businesses and the character of our commercial corridor.”
Contact Colin Robinette at crobinette@oxy.edu
![]()